Caywood Addition, Amended Preliminary P.U.D. Kenny Hill from Poe and Associates presented
information on behalf of the developer. Mr. Hill presented the
information regarding the amendments. He stated the changes are as follows:
1. Six acres have been added to the
property,
2. The lots are to be smaller,
but average 10,000 sq. feet,
3. The 1st Phase will be at 159th Street, and
4. There will be a 24” water main at 159th Street.
Quentin Coon arrived at 5:44 p.m.
Mr. Hill also stated:
5. The street right of ways
will be to the new City standards, and
6. The lots will have 6’ side yard minimums.
Joe Robertson, Quentin Coon and Ron Roberts were concerned about the density and lot sizes at the minimums for the district.
Jeff Bridges stated there is to be an 8’ sidewalk on
the collector street, which is Basswood. Joe Robertson asked about the
landscaping in Reserve D and suggested that the Reserve be developed by
adding playground equipment during Phase 1.
Lynn Heath stated that
Honeysuckle goes through to Basswood and there is access from Honeysuckle to
Reserve D.
Ron Roberts confirmed that
Reserve E is drainage only. He commented that the 6’ sideyard will equal a
12’ separation; he would prefer 8’ minimum sideyards.
Motion was made by Joe
Robertson to recommend approval to the Planning Commission of Caywood
Addition Amended Preliminary P.U.D. with the following conditions:
1. 8’ sidewalk width on collector streets.
2. 8’ minimum sideyard.
3. Develop Reserve D by
landscaping and adding playground equipment during Phase 1.
Motion was seconded by Ron Roberts. Motion carried