|
SP-2005-24: Review the Revised site plan for Advance Storage
located at 1403 W. Ledgerwood.
From
Les Mangus memo: The Final Site Plan for the Advance Storage Expansion is
generally in order. The lighting and signage need some attention to meet the
requirements. The placement of landscaping for screening purposes south of
the new buildings, and the placement of the brick fence column on the 20 ft.
utility easements are problems for future maintenance of the existing sewer
lines, and should be prohibited. It appears that the entire site plan east of
the creek could be shifted north 5-10 feet to accommodate the easement.
Several comments are listed in the Staff Review, but with some direction from
the Committee could probably be worked out with the construction documents.
Owner
Keith McCoy and Mike Decker of Spangenberg Phillips Architects presented the
revised plans. Mike Decker explained the drainage way problem through the
site. The 6 existing buildings will be maintained and the remainder of the
site will be developed into the same facility. A bridge will be constructed
to connect the 2 sides of the development over the drainage way. Along Ledgerwood
will be installed a brick and wrought iron fence that will line the street
and connect to the corner of the building. Landscape will be provided in the
right-of-way up to the corner. The existing entrance will remain, but be
designated for emergency vehicles only. A new drive will be created to the
east with a direct path leading to the office building. The office building
will have a tower element added and more parking spaces are being designed.
Mike explained the office/apartment design for the on-site manager which will
also include a garage for their own storage and vehicle. He explained the
tempered storage building. There will be a flip up gate at the entrance with
a security code for access. Another gate will be used for the emergency
vehicle entrance. The additional buildings on the east side of the drainage
way will match the existing buildings on the site which are metal panel with
green roof systems. The residential area to the south will be buffered with
buildings and landscaping. The storage buildings will be kept 100 feet from
the property lines adjacent to the residential area. Mike explained the site
grading plan, utility plan which shows the sewer line that runs down the
south property line, landscape plan, lighting plan, and elevation drawings.
The size of the building has been reduced to allow for the 10’ buffer in
front of the building.
Don
Kimble asked if the existing trees
would have to be removed for the development. Mike said they would be kept.
Don
Kimble referred to the memo from Les
and Mike was given a copy. Don said part of the fence and brick piers are
over the lines and need adjusted. Mike said he has changed his plan making
the fence wrought iron or chain link. He said they will not build into the
easement.
Jeff
Bridges asked about the landscaping south of the new buildings. Mike said the
revised submittal has more dense trees at the openings and a line of trees
behind the buildings. There was discussion about prohibiting the trees due to
the sewer easement. Mike said he has located the sewer line on the south and
plans to plant 6 feet from that utility line.
There
was general discussion about the PUD to the south.
The
lighting plan was discussed. Mike Decker said there are some areas on the
plan that do not meet the minimum requirements. Don Kimble was concerned
about the lack of lighting on the bridge. He said that would be a major part
of the success of the project.
Don
Kimble said he wanted to see the
landscape and lighting shown on the elevation plans.
Clark
Nelson asked why the concrete fence did not extend all the way around to the
east. Mike said there is a 20’ section of land that will have dense
landscaping for the residential neighbor. There was discussion about plants
vs. concrete walls as screening.
Jeff
asked if the fence is on the inside or outside of the landscaping. Mike said
the fence stops at each corner of the building to form a security wall. Don Kimble asked Staff if the required maximum fence height is 6 or 8 feet.
Doug
Allison asked about sign plans. Mike
said Les asked for actual dimensions of the sign. He plans to relocate the
existing sign to just east of the new entrance. The sign is 112 square feet. Don Kimble said the size and color of the letters are not called out on the plan. Mike said he
would get that to Les.
Don
Kimble made a motion to approve
the plan as presented with the following conditions:
- The submittal meets all Staff review and approval comments.
- The applicant check for the height restriction on fences on the
south and east property lines.
Clark
Nelson seconded the motion. There
was further discussion.
Don
Kimble amended his original
motion to include the requirement of minimum 1 foot-candle at the bridge.
Clark Nelson seconded the amendment to the original motion. Motion carried 5/0.
|